South Carolina

Who may prepare a stormwater plan in South Carolina

South Carolina requires a credentialed preparer only in some cases. Sites above 2 acres.

The answer

Conditional

South Carolina requires a credentialed preparer only in some cases. Sites above 2 acres.

What triggers it: Sites above 2 acres.

Credentials that qualify

  • SC-licensed Professional Engineer (Title 40, Chapter 22)
  • SC-registered Landscape Architect (Title 40, Chapter 28, Section 10, item (b))
  • SC Tier B Land Surveyor (Title 40, Chapter 22)
  • Federal government employee as described in Title 40, Chapter 22, Section 280(A)(3)

Gate is acreage-tiered, not flat. Sites disturbing 2 acres or less, not part of a larger common plan of development, have no named-credential requirement to prepare the C-SWPPP (a Coastal Zone carve-out at Section 3.1.2.D pulls some sub-2-acre sites near a coastal receiving water into the same gated requirement). Above 2 acres, the C-SWPPP must be prepared, certified and stamped by one of the four routes above — no CPESC/CEPSCI route exists for this design/stamp role, correcting and confirming this dataset's prior 'CPESC not accepted as signer' finding. A narrower, genuinely mandatory PE-seal requirement applies only where the site is both subject to Regulation 72-400 and disturbs 5+ acres; exactly what triggers 72-400 applicability was not independently confirmed (it appears tied to permanent stormwater/dam-safety-linked structures). Routine inspections are a separate obligation from SWPPP preparation: Section 4.2.E allows the C-SWPPP preparer, someone with equivalent registration, someone they directly supervise, or a person certified through an SCDES-approved Construction Site Inspector Certification Course (Clemson's CEPSCI is the recognized course) — stateCourseRequired is false because that course is one of several qualifying options for inspection, not a mandatory single path, and does not confer SWPPP-preparation authority.

Verified2026 SC NPDES CGP (SCR100000), Section 3.1.2.B-D and Section 3.1.3 (Signatory Requirements); inspector qualifications at Section 4.2.ESource

What this means for a generated plan

Where a credential applies, or where we cannot confirm that none does, treat a generated document as a complete draft for a credentialed preparer to review, amend and sign. It is not by itself a compliant filed plan, and ours says so on its face.

Screen a South Carolina site, credential answer included

Screen your site

Runs in your browser

Total land disturbance over the whole project, including staging and access. This decides whether you need a permit at all.

Optional. If you phase the work, the most that will be disturbed at once. Leave blank if the whole site is open together. The stabilisation deadline turns on this figure, not the total.

A half acre lot inside a 40 acre subdivision is covered even though the lot alone is under the threshold. This is the most commonly missed trigger in the permit.

Receiving water and site conditions(optional, but they change the inspection frequency)

May allow a reduced inspection frequency during the seasonally dry period.

EPA keeps permitting authority in Indian country even inside a state that runs its own programme.

No account, no card, nothing transmitted.

What people ask about preparing a SWPPP in South Carolina

Do I need a qualified preparer for a SWPPP in South Carolina?

South Carolina requires a credentialed preparer only in some cases. Sites above 2 acres.

Does a professional engineer have to stamp the plan in South Carolina?

A PE stamp is required in South Carolina. Trigger: Construction sites subject to SC Regulation 72-400 that disturb 5 acres or more must have the C-SWPPP prepared, certified and sealed specifically by a professional engineer licensed to practice in SC (Title 40, Ch. 22) — at this threshold the landscape-architect, Tier B surveyor and federal-employee alternatives do not qualify; only a PE seal satisfies it..

Get the answer before somebody starts drafting

Screening is free and runs in your browser. Pro generates the plan document and keeps the record the permit requires.