Free screening, both regimes
Screen a site against the permits that govern it
No account, no card, and no request. Both engines that answer this are the same ones behind the API and the paid product, and they run in this tab, so your location, acreage and dates are never transmitted.
Only need one regime? Stormwater only · Section 404 only
Enter the site
State, activity, and the acreage the project will disturb. Say whether it is part of a larger common plan of development or sale, which is the trigger most people miss.
Add what you know about the receiving water
Whether the site discharges to a sediment or nutrient impaired water, or a Tier 2, 2.5 or 3 water. If you have not checked, leave it as not checked and the answer will say so rather than assume.
Read the determination
The coverage verdict, the governing permit, the requirements with the permit section behind each one, the eligibility screens and the credential gate, plus the full derivation so every conclusion shows its reasoning.
We do not perform site inspections
The permit requires a physical inspection by a qualified person on a schedule, and that person has to be standing on the site. We generate the plan and maintain the inspection record. We are a compliance documentation engine, not compliance.
In credential gated states our document is a draft
Where a state requires a credentialed preparer, what we generate is a complete draft for that person to review, amend and sign. It is not by itself a filed plan, and it says so on the document. We would rather lose the sale than have you file something that is not valid in your state.
An unread jurisdiction reads as unread
Where we have not read a state's permit we do not print a plausible number. The page says not verified, names the agency and links it. We never infer a requirement we did not read in a permit, and an honest gap always beats a confident guess.
PermitBird reports publicly published permit rules and cites the source and effective date behind each one. It is not legal or engineering advice and it is not a permit. Section 404 determinations do not replace a jurisdictional determination or a pre-construction notification filed with the district. We do not perform wetland delineations. We do not perform the physical site inspections a stormwater permit requires; we generate the plan and keep the record. Where a jurisdiction requires a credentialed preparer, the document we generate is a draft for that person to review and sign. Always confirm against your permitting authority's current rules before you break ground.
91 FR 768 · effective 2026-03-15
Also affecting a wetland, stream or other water of the United States?
A separate determination against all 57 nationwide permits under Clean Water Act Section 404. Change a number and the verdict updates with the rule that produced it.
- Permits compiled
- 57 of 57
- every one sourced to the final rule
- Carrying acreage limits
- 20
- the rest state no acreage cap
- District conditions
- 2 of 38
- not yet compiled, and we say so
- State 401 certifications
- 4 of 54
- not yet compiled, and we say so
Live preview
Nationwide permit, notification required
A nationwide permit looks available, but you must file a pre-construction notification before you build.
Computed against the 2026 nationwide permits, effective 2026-03-15.
Pre-construction notification
Required. The district engineer has 45 calendar days to review a complete notification.
Permanent loss is greater than 0.1 acres, which triggers a pre-construction notification.
Verified0.35 acres measured against the 0.1 acres notification trigger.
91 FR 768 - Reissuance and Modification of Nationwide Permits (final rule, 8 Jan 2026)NWP 14 requires notification in defined circumstances. Check them against your project.
VerifiedPCN required if: (1) the loss of waters of the United States exceeds 1/10-acre; or (2) there is a discharge in a special aquatic site, including wetlands.
91 FR 768 - Reissuance and Modification of Nationwide Permits (final rule, 8 Jan 2026)NWP 3 requires notification in defined circumstances. Check them against your project.
VerifiedRequired for activities under paragraph (b) - removal of accumulated sediments and debris outside the immediate vicinity of existing structures.
91 FR 768 - Reissuance and Modification of Nationwide Permits (final rule, 8 Jan 2026)
Permits screened (3)
Permanent loss is within the 1/2 acre limit NWP 14 applies in non-tidal waters.
Verified0.35 acres of permanent loss in non-tidal waters, measured against the 1/2 acre limit. 1/2-acre limit applies in non-tidal waters; a lower 1/3-acre limit applies in tidal waters.
91 FR 768 - Reissuance and Modification of Nationwide Permits (final rule, 8 Jan 2026)
No impact limit has been transcribed for NWP 3 yet, so eligibility cannot be determined here.
UnverifiedPermitBird returns an explicit gap rather than an inferred limit. Read the permit text or contact the district office.
91 FR 768 - Reissuance and Modification of Nationwide Permits (final rule, 8 Jan 2026)
Permanent loss exceeds the 1/10 acre limit for NWP 18.
Verified0.35 acres of permanent loss measured against a 1/10 acre limit.
91 FR 768 - Reissuance and Modification of Nationwide Permits (final rule, 8 Jan 2026)
Sacramento District
Regional conditions are not compiled. This determination covers the federal layer only.
District regulatory officeCalifornia Section 401
Section 401 conditions are compiled and applied above.
What we hold for this stateWhat this determination does not cover
- The mapping from "Road, highway or railway crossing" to candidate permits is unverified. Confirm the permit selection against the permit text.
- Impact limits are not yet transcribed for NWP 3.
- Regional conditions for the Sacramento District are not compiled. They can narrow or remove a nationwide permit, so confirm them with the district before relying on this.
Sources
- 91 FR 768 - Reissuance and Modification of Nationwide Permits (final rule, 8 Jan 2026)
- Full text of 91 FR 768 (GPO via federalregister.gov)
Project impact entered: 0.35 acres permanent loss, 120 linear feet of stream bed.
Screening answers the question. The permit makes you keep the record.
A covered operator must hold a written site specific plan and retain the inspection and corrective action log for years. That is the paid product. Section 404 screening stays free and keyless forever.