Who may prepare a stormwater plan in Tennessee
Tennessee requires a credentialed preparer only in some cases. Sites above 5 acres.
The answer
ConditionalTennessee requires a credentialed preparer only in some cases. Sites above 5 acres.
What triggers it: Sites above 5 acres.
Credentials that qualify
- Registered professional engineer (TN)
- Registered landscape architect (TN)
- Certified Professional in Erosion and Sediment Control (CPESC)
- Completion of TDEC's "Level II Design Principles for Erosion Prevention and Sediment Control for Construction Sites" course
Gate is acreage-based, not a single mandatory credential: sites 5 acres or less of disturbance have no SWPPP-preparer qualification requirement (optional TDEC templates available); sites over 5 acres require the narrative be prepared by someone meeting one of the routes above, and the permit's own list is open ("such as, but not limited to"). The separately-triggered PE/landscape-architect stamp requirement applies only to engineering design of sediment basins/structural controls at 10+ acre (or 5+ acre for sensitive waters) drainage areas — commonly conflated with a full-SWPPP PE requirement, which this permit does not impose. Reconfirms and supersedes the prior entry, which was sourced to the 2011 permit and flagged for reconfirmation against the 2021 version.
What this means for a generated plan
Where a credential applies, or where we cannot confirm that none does, treat a generated document as a complete draft for a credentialed preparer to review, amend and sign. It is not by itself a compliant filed plan, and ours says so on its face.
Screen a Tennessee site, credential answer included
What people ask about preparing a SWPPP in Tennessee
Do I need a qualified preparer for a SWPPP in Tennessee?
Tennessee requires a credentialed preparer only in some cases. Sites above 5 acres.
Does a professional engineer have to stamp the plan in Tennessee?
A PE stamp is required in Tennessee. Trigger: Engineering design of sediment basins or equivalent structural sediment controls must be prepared by a TN-registered PE or landscape architect and signed/sealed per T.C.A. Title 62, Ch. 2, required for construction sites with 10 or more acres draining to a single outfall, or 5 or more acres if draining to waters with unavailable parameters or Exceptional Tennessee Waters..