West Virginia
Who may prepare a stormwater plan in West Virginia
We found no state level preparer credential for West Virginia. On what we verified, an operator may adopt the plan without a credentialed signature. Local ordinances can still be stricter.
The answer
None foundWe found no state level preparer credential for West Virginia. On what we verified, an operator may adopt the plan without a credentialed signature. Local ordinances can still be stricter.
Part II.H states the SWPPP shall be prepared by a 'Qualified Person,' but that term is never defined in the permit — absent from Appendix C Definitions and not recurring as a defined term elsewhere. No state-recognized course, license, or certification body is named, so the gate is open: any operator-designated qualified individual may prepare the SWPPP. A PE stamp is genuinely not required to prepare the SWPPP; the sole PE/surveyor mention in the whole permit (Part IV.D.2) is an optional alternative path for demonstrating final site stabilization, not a gate on plan authorship. Commercial preparer-training courses exist in the market but are not referenced or required by the permit text itself.
What this means for a generated plan
On what we verified, an operator may adopt a generated plan here without a credentialed signature. Local ordinances can still impose a stricter gate than state law, so check the county or municipality as well.
Screen a West Virginia site, credential answer included
What people ask about preparing a SWPPP in West Virginia
Do I need a qualified preparer for a SWPPP in West Virginia?
We found no state level preparer credential for West Virginia. On what we verified, an operator may adopt the plan without a credentialed signature. Local ordinances can still be stricter.
Does a professional engineer have to stamp the plan in West Virginia?
Practice act citations are routinely overstated on this point. A PE stamp is not required as a general matter in most states with no preparer gate, and where we have not verified it we will not assert either answer. Confirm with the state board or the permitting authority.
Get the answer before somebody starts drafting
Screening is free and runs in your browser. Pro generates the plan document and keeps the record the permit requires.