Plan before Notice of Intent
SWPPP must be prepared prior to NOI submission
An operator must prepare a SWPPP before submitting the NOI for authorization under this permit.
Alaska
Alaska issues its own construction general permit. We have read General Permit for Discharges from Large and Small Construction Activities (Construction General Permit), Permit Number AKR100000 and list below the requirements we could cite to it, with the scope limits stated plainly. Screen your own acreage further down.
Who may prepare the plan
Conditional, depends on the siteAlaska gates plan preparation only above a threshold this site does not meet. The gate applies above 20 acres. This site is 3 acres. On what we have verified, a generated plan can be adopted without a credentialed signature.
Qualifying routes
Alaska is tiered by acreage: nothing under 5 acres, AK-CESCL above 20. The preparer must also conduct a site visit before writing the plan. Reconciled against the jurisdiction registry, which found a preparer requirement this entry had missed. Where the two sources disagreed we kept the stricter answer.
Coverage trigger
The project disturbs 3 acres, at or above the 1 acre threshold, so it needs permit coverage.
The trigger people miss is the second one. A half acre lot inside a 40 acre subdivision is covered, because the larger common plan of development or sale is what counts, not the lot.
Worked for a three acre site with the receiving water unconfirmed. Each line says why it attached to this site rather than in general. Check the notes above for the site sizes this permit does not cover.
SWPPP must be prepared prior to NOI submission
An operator must prepare a SWPPP before submitting the NOI for authorization under this permit.
Submit before commencing construction activities; the exact lead time is not recorded for this id.
Why this applies here: This is the deadline for a new site. A transfer to a new operator or an emergency related project has a different deadline.
Each operator must submit an NOI to be authorized to discharge under this permit at least five business days prior to commencement of construction activities.
Submit the Notice of Termination once a termination condition is met; the exact deadline is not recorded for this id.
A permittee must submit an NOT within 30 calendar days after one or more of the following conditions have been met:
At least once every 7 calendar days.
Why this applies here: You have not confirmed whether the site discharges to an impaired or high quality water. If it does, the increased frequency applies instead and this answer changes.
Once every seven calendar days; or
Once every 14 calendar days.
Why this applies here: You have not confirmed whether the site discharges to an impaired or high quality water. If it does, the increased frequency applies instead and this answer changes.
Once every 14 calendar days and within 24 hours of the end of a storm event that resulted in a discharge from the site; or
qualified person as defined in Appendix C
Why this applies here: This is why Basinwise cannot perform your inspections. The permit requires a trained person physically on the site.
An inspection must be conducted by a qualified person (as defined in the Appendix C) provided by a permittee.
Confirm the exact minor-fix deadline against the cited permit section.
For conditions that are easily remedied, the permittee must initiate appropriate steps to correct the problem within 24 hours from the time of discovery and correct the problem as soon as practicable; or
Within 7 calendar days of discovery.
If installation of a new control measure is needed or an existing control measure requires redesign and reconstruction or replacement, the permittee must install the new or modified measure and make it operational within seven calendar days from the time of discovery.
Provide and maintain a natural buffer or equivalent erosion and sediment controls near surface waters; the exact distance is not recorded for this id.
A permittee must maintain natural buffer areas at stream crossings and around the edge of any waters of the U.S. ... The buffer must be a minimum of 25 feet wide, or the width as required by local ordinance.
Record the condition within 24 hours of identifying it, and record completion within 24 hours of completing the work.
A permittee must document the following information in the corrective action log, within 24 hours of discovery of any condition listed in Part 8.1 or upon notification from a subcontractor.
Retain inspection reports and the corrective action log for at least 3 years from the date permit coverage expires or is terminated.
Why this applies here: The clock runs from permit expiry or termination, not from when the record was written, so on a multi year project every record stays live for the whole project plus three years.
A permittee must retain the following records... for a minimum of three years from the date that authorization under this permit expires or is terminated.
Your acreage, your receiving water, your answer. Runs in your browser, nothing is transmitted.
This is EPA's list, from the 2022 Construction General Permit. It does NOT govern in Alaska, where the state issues its own permit and sets its own contents. It is here as a shape to expect, not as the requirement you will be held to.
Read the permit itself at the source document.
Alaska issues its own construction general permit, and we have read General Permit for Discharges from Large and Small Construction Activities (Construction General Permit), Permit Number AKR100000. The requirements listed on this page, such as inspection frequency, who may inspect, stabilisation, corrective action and record retention, are cited to that permit rather than to EPA's. Anything we have not transcribed is left out instead of assumed to match the federal rule, and the scope note on this page says which sites the permit does not cover. Confirm the current permit and any site-size variant with Alaska Department of Environmental Conservation (Alaska DEC), Wastewater Discharge Authorization Program.
Alaska gates plan preparation only above a threshold this site does not meet. The gate applies above 20 acres. This site is 3 acres. On what we have verified, a generated plan can be adopted without a credentialed signature.
The inspection frequency is set by the Alaska construction general permit, which we have not read. Confirm it with Alaska Department of Environmental Conservation (Alaska DEC), Wastewater Discharge Authorization Program.
Screening is free. Pro generates the site specific plan document and retains the inspection and corrective action log.