Plan before Notice of Intent
Develop the plan before submitting your Notice of Intent for coverage.
The Permittee is required to develop the site's SWPPP prior to submitting the NOI.
Hawaii
Hawaii issues its own construction general permit. We have read NPDES General Permit Authorizing Discharges of Storm Water Associated with Construction Activity (HAR Chapter 11-55, Appendix C) and list below the requirements we could cite to it, with the scope limits stated plainly. Screen your own acreage further down.
Who may prepare the plan
No preparer credential foundNo preparer credential was found for Hawaii. On what we have verified, a generated plan can be adopted by the operator without a credentialed signature. Local ordinances can still be stricter than state law.
No preparer credential found in the reviewed sources. Not exhaustively verified; confirm with the state agency and any local ordinance.
No permit section cited. Confirm this with your permitting authority.
Coverage trigger
The project disturbs 3 acres, at or above the 1 acre threshold, so it needs permit coverage.
The trigger people miss is the second one. A half acre lot inside a 40 acre subdivision is covered, because the larger common plan of development or sale is what counts, not the lot.
Worked for a three acre site with the receiving water unconfirmed. Each line says why it attached to this site rather than in general. Check the notes above for the site sizes this permit does not cover.
Develop the plan before submitting your Notice of Intent for coverage.
The Permittee is required to develop the site's SWPPP prior to submitting the NOI.
Submit before commencing construction activities; the exact lead time is not recorded for this id.
Why this applies here: This is the deadline for a new site. A transfer to a new operator or an emergency related project has a different deadline.
The owner or operator shall submit a complete notice of intent no later than thirty days before the proposed starting date of the construction activity or thirty days before the expiration date of the applicable notice of general permit coverage.
When all construction activities have ceased, the permittee must submit a completed Notice of Cessation; the department must receive it within 7 calendar days after the end of the month in which activities ceased.
When all construction activities have ceased, the permittee shall submit to the department a completed Notice of Cessation. The department shall receive this information within 7 calendar days after the end of the month.
At least once every 7 calendar days.
Why this applies here: You have not confirmed whether the site discharges to an impaired or high quality water. If it does, the increased frequency applies instead and this answer changes.
At least once every 7 calendar days; or
Once every 14 calendar days and within 24 hours of a storm event producing 0.25 inches or more of rain in a 24-hour period, or 3.25 inches or more of snow accumulation in a 24-hour period.
Why this applies here: You have not confirmed whether the site discharges to an impaired or high quality water. If it does, the increased frequency applies instead and this answer changes.
Once every 14 calendar days and within 24 hours of the occurrence of a storm event as specified in section 9.1.2.1.1. or section 9.1.2.1.2. ... A storm event that produces 0.25 inches or more of rain within a 24-hour period.
A person knowledgeable in the principles and practice of erosion and sediment controls and pollution prevention, who possesses the skills to assess conditions at the construction site that could impact storm water quality, and the skills to assess the effectiveness of any storm water controls selected and installed to meet the requirements of this permit.
Why this applies here: This is why Basinwise cannot perform your inspections. The permit requires a trained person physically on the site.
A "qualified person" is a person knowledgeable in the principles and practice of erosion and sediment controls and pollution prevention, who possesses the skills to assess conditions at the construction site that could impact storm water quality, and the skills to assess the effectiveness of any storm water controls selected and installed to meet the requirements of this permit.
Initiate immediately whenever earth-disturbing activities have permanently or temporarily ceased on any portion of the site; 'immediately' means as soon as practicable, but no later than the end of the next work day.
Why this applies here: This applies at both land disturbance amounts.
The permittee shall initiate soil stabilization measures immediately whenever earth-disturbing activities have permanently or temporarily ceased on any portion of the site.
Initiate immediately after discovering the problem and complete by the close of the next work day, if the problem does not require significant repair/replacement or can be corrected through routine maintenance; extendable to 7 calendar days with documentation of infeasibility.
Initiate work to fix the problem immediately after discovering the problem, and complete such work by the close of the next work day, if the problem does not require significant repair or replacement, or if the problem can be corrected through routine maintenance.
When installation of a new erosion or sediment control or a significant repair is needed, install and make it operational, or complete the repair, by no later than 7 calendar days from the time of discovery where feasible.
When installation of a new erosion or sediment control or a significant repair is needed, the permittee shall install the new or modified control and make it operational, or complete the repair, by no later than 7 calendar days from the time of discovery where feasible.
An undisturbed natural buffer and sediment controls are required between disturbed portions of the site and any receiving state waters located within 50 feet of the project's earth disturbances, unless an alternative (narrower buffer with double sediment control, or double sediment control alone plus 7-day stabilization if a buffer is infeasible) is used.
The permittee shall provide and maintain an area of undisturbed natural buffer and sediments controls between the disturbed portions of the site and any receiving state waters that are located within 50 feet of the project's earth disturbances.
The permittee must complete an inspection report within 48 hours of completing any site inspection.
The permittee must complete an inspection report within 48 hours of completing any site inspection.
Within 24 hours of discovering a triggering condition, document the condition identified, its nature, and the date/time and manner of identification.
Within 24 hours of discovering the occurrence of one of the triggering conditions in section 10.2.1. at the site, the permittee shall document the following information:
Inspection reports must be retained for at least three years from the date the permit coverage expires or is terminated.
Why this applies here: The clock runs from permit expiry or termination, not from when the record was written, so on a multi year project every record stays live for the whole project plus three years.
All inspection reports completed for this section must be retained for at least three years from the date that the permit coverage expires or is terminated.
Your acreage, your receiving water, your answer. Runs in your browser, nothing is transmitted.
This is EPA's list, from the 2022 Construction General Permit. It does NOT govern in Hawaii, where the state issues its own permit and sets its own contents. It is here as a shape to expect, not as the requirement you will be held to.
Read the permit itself at the source document.
Hawaii issues its own construction general permit, and we have read NPDES General Permit Authorizing Discharges of Storm Water Associated with Construction Activity (HAR Chapter 11-55, Appendix C). The requirements listed on this page, such as inspection frequency, who may inspect, stabilisation, corrective action and record retention, are cited to that permit rather than to EPA's. Anything we have not transcribed is left out instead of assumed to match the federal rule, and the scope note on this page says which sites the permit does not cover. Confirm the current permit and any site-size variant with Hawaii Department of Health (DOH), Clean Water Branch (CWB).
No preparer credential was found for Hawaii. On what we have verified, a generated plan can be adopted by the operator without a credentialed signature. Local ordinances can still be stricter than state law.
The inspection frequency is set by the Hawaii construction general permit, which we have not read. Confirm it with Hawaii Department of Health (DOH), Clean Water Branch (CWB).
Screening is free. Pro generates the site specific plan document and retains the inspection and corrective action log.