Plan before Notice of Intent
The construction plan/SWP3 must be submitted to the appropriate reviewing agency (SWCD, MS4, or IDEM) prior to initiation of any land-disturbing activity, and the project site owner must receive notification from the reviewing agency that the plan meets permit requirements BEFORE a complete NOI may be submitted to the commissioner.
After the project site owner has received notification from the reviewing agency that the construction plan/SWP3 meets the requirements of this permit and any applicable municipal separate storm sewer system (MS4) ordinance a complete NOi must be submitted to the commissioner.