Plan before Notice of Intent
SWPPP must be completed prior to submitting the NOI
The SWPPP shall be completed prior to the submittal of a NOI to the Department to be covered under this permit and shall be updated as appropriate.
Iowa
Iowa issues its own construction general permit. We have read NPDES General Permit No. 2, Storm Water Discharge Associated with Construction Activities and list below the requirements we could cite to it, with the scope limits stated plainly. Screen your own acreage further down.
Who may prepare the plan
No preparer credential foundNo preparer credential was found for Iowa. On what we have verified, a generated plan can be adopted by the operator without a credentialed signature. Local ordinances can still be stricter than state law.
Iowa identifies this permit by sequence number rather than a state-prefixed alphanumeric code. Credential: no preparer credential; the permit contains no reference to a professional engineer, CPESC or licensure. It requires only that 'SWPPPs shall be prepared in accordance with good engineering practices' and defines qualified personnel by capability and knowledge.
No permit section cited. Confirm this with your permitting authority.
Coverage trigger
The project disturbs 3 acres, at or above the 1 acre threshold, so it needs permit coverage.
The trigger people miss is the second one. A half acre lot inside a 40 acre subdivision is covered, because the larger common plan of development or sale is what counts, not the lot.
Worked for a three acre site with the receiving water unconfirmed. Each line says why it attached to this site rather than in general. Check the notes above for the site sizes this permit does not cover.
SWPPP must be completed prior to submitting the NOI
The SWPPP shall be completed prior to the submittal of a NOI to the Department to be covered under this permit and shall be updated as appropriate.
Submit before commencing construction activities; the exact lead time is not recorded for this id.
Why this applies here: This is the deadline for a new site. A transfer to a new operator or an emergency related project has a different deadline.
For storm water discharge associated with industrial activity for construction activities, such activities shall not commence until an authorization has been issued for the project by the Department.
Submit the Notice of Termination once a termination condition is met; the exact deadline is not recorded for this id.
Within 30 days after final stabilization at a construction site (as defined in Part VIII of this permit), the operator or owner of the facility shall submit a Notice of Discontinuation (NOD) to the Department.
At least once every 7 calendar days.
Why this applies here: You have not confirmed whether the site discharges to an impaired or high quality water. If it does, the increased frequency applies instead and this answer changes.
Qualified personnel (provided by the discharger) shall inspect disturbed areas of the construction site that have not been stabilized with a perennial, vegetative cover of sufficient density to preclude erosion at least once every seven calendar days.
Qualified personnel: individuals capable enough and knowledgeable enough to perform the required functions adequately well to ensure compliance
Why this applies here: This is why Basinwise cannot perform your inspections. The permit requires a trained person physically on the site.
"Qualified personnel" means those individuals capable enough and knowledgeable enough to perform the required functions adequately well to ensure compliance with the relevant permit conditions and requirements of the Iowa Administrative Code.
Immediately, once activity has permanently ceased on a portion of the site, or temporarily ceased and will not resume for more than 14 calendar days
Why this applies here: This applies at both land disturbance amounts.
Stabilization of disturbed areas must, at a minimum, be initiated immediately whenever any clearing, grading, excavating or other earth disturbing activities have permanently ceased on any portion of the site or temporarily ceased on any portion of the site and will not resume for a period exceeding 14 calendar days.
Confirm the exact minor-fix deadline against the cited permit section.
If the permittee determines that making these changes at the construction site within 72 hours of the inspection is impracticable, the permittee shall document in the SWPPP why it is impracticable and indicate an estimated date by which the changes will be made.
Confirm the exact major-fix deadline against the cited permit section.
If the permittee determines that making these changes at the construction site within 72 hours of the inspection is impracticable, the permittee shall document in the SWPPP why it is impracticable and indicate an estimated date by which the changes will be made.
Provide and maintain a natural buffer or equivalent erosion and sediment controls near surface waters; the exact distance is not recorded for this id.
Provide and maintain natural buffers around waters of the United States, direct storm water to vegetated areas and maximize storm water infiltration to reduce pollutant discharges, unless infeasible.
Complete the inspection report within 24 hours of completing the site inspection.
the storm water pollution prevention measures identified in the SWPPP shall be revised at the construction site as appropriate as soon as practicable after the inspection and added to the SWPPP within 7 calendar days of the inspection.
Document the condition and its completion; the exact documentation deadline is not recorded for this id.
added to the SWPPP within 7 calendar days of the inspection.
Retain inspection reports and the corrective action log for at least 3 years from the date permit coverage expires or is terminated.
Why this applies here: The clock runs from permit expiry or termination, not from when the record was written, so on a multi year project every record stays live for the whole project plus three years.
For a period of at least three years from the date of the document or the date the site is finally stabilized and a NOD has been submitted, the permittee shall retain copies of SWPPPs, all reports required by this permit, and all records used to complete the NOI.
Your acreage, your receiving water, your answer. Runs in your browser, nothing is transmitted.
This is EPA's list, from the 2022 Construction General Permit. It does NOT govern in Iowa, where the state issues its own permit and sets its own contents. It is here as a shape to expect, not as the requirement you will be held to.
Read the permit itself at the source document.
Iowa issues its own construction general permit, and we have read NPDES General Permit No. 2, Storm Water Discharge Associated with Construction Activities. The requirements listed on this page, such as inspection frequency, who may inspect, stabilisation, corrective action and record retention, are cited to that permit rather than to EPA's. Anything we have not transcribed is left out instead of assumed to match the federal rule, and the scope note on this page says which sites the permit does not cover. Confirm the current permit and any site-size variant with Iowa Department of Natural Resources (Iowa DNR).
No preparer credential was found for Iowa. On what we have verified, a generated plan can be adopted by the operator without a credentialed signature. Local ordinances can still be stricter than state law.
The inspection frequency is set by the Iowa construction general permit, which we have not read. Confirm it with Iowa Department of Natural Resources (Iowa DNR).
Screening is free. Pro generates the site specific plan document and retains the inspection and corrective action log.