SWPPP requirements in Mississippi

Mississippi issues its own construction general permit. We have read Large Construction General Permit for Land Disturbing Activities of Five (5) or More Acres (MSR10) and list below the requirements we could cite to it, with the scope limits stated plainly. Screen your own acreage further down.

Who may prepare the plan

No preparer credential found

No preparer credential was found for Mississippi. On what we have verified, a generated plan can be adopted by the operator without a credentialed signature. Local ordinances can still be stricter than state law.

No preparer credential found in the reviewed sources. Not exhaustively verified; confirm with the state agency and any local ordinance.

No permit section cited. Confirm this with your permitting authority.

Coverage trigger

Worked through at 3 acres

The project disturbs 3 acres, at or above the 1 acre threshold, so it needs permit coverage.

The trigger people miss is the second one. A half acre lot inside a 40 acre subdivision is covered, because the larger common plan of development or sale is what counts, not the lot.

Read these before you act on the answer

  • Requirements below are what we have read and cited directly from Large Construction General Permit for Land Disturbing Activities of Five (5) or More Acres (MSR10), not the federal CGP. A category we have not yet transcribed from this permit is omitted here rather than assumed to match EPA's rule.
  • This overlay covers only the MSR10 Large Construction General Permit (5+ acres). Mississippi also issues a separate Small Construction General Permit (1 to <5 acres), administratively continued past its April 30, 2024 expiration; its text was not fetched/verified in this session and is not represented here. Not found in the fetched MSR10 text: a fixed day-count NOI lead time before starting construction; a distinct inspection-report-filing deadline; an increased-inspection-frequency trigger for sensitive/impaired waters; a reduced-inspection-frequency provision for arid/drought conditions (MS's only drought-related provision affects stabilization method, not inspection frequency). MS does not use an acreage-tiered final-stabilization completion deadline; final stabilization is defined by a 70% vegetative cover density threshold instead.
  • No preparer credential was found for Mississippi. On what we have verified, a generated plan can be adopted by the operator without a credentialed signature. Local ordinances can still be stricter than state law.
  • Basinwise does not perform the physical site inspections the permit requires. Those must be carried out on site by a qualified person.

What the permit requires of a Mississippi site

Worked for a three acre site with the receiving water unconfirmed. Each line says why it attached to this site rather than in general. Check the notes above for the site sizes this permit does not cover.

Filing

Plan before Notice of Intent

A site-specific SWPPP must be submitted together with the Large Construction Notice of Intent (LCNOI); owners/operators are authorized to discharge only upon receipt of written notification of approval of coverage.

Owners or operators are authorized to discharge storm water associated with large construction activity under the terms and conditions of this permit only upon receipt of written notification of approval of coverage by the Permit Board staff.
VerifiedMSR10 Permit, ACT4, S-2; ACT3, S-1(4)Source
Notice of Termination deadline
30

Within 30 days of final stabilization, a completed RFT form and photographs of the stabilized site must be submitted.

Within thirty (30) days of final stabilization (see Definition of Final Stabilization (1)) for a covered project, a completed Request for Termination (RFT) of Coverage form ... and colored photographs of the stabilized site shall be submitted to the Permit Board.
VerifiedMSR10 Permit, ACT10, S-1Source

Inspections

Inspection frequency, option 1
7

Inspection must be performed by qualified personnel at least weekly for a minimum of four inspections per month, and as often as necessary; controls and outfalls must also be inspected after rain events that produce a discharge.

Why this applies here: You have not confirmed whether the site discharges to an impaired or high quality water. If it does, the increased frequency applies instead and this answer changes.

Inspection of all receiving streams (if feasible), outfalls, erosion and sediment controls and other SWPPP requirements shall be performed during permit coverage ... shall be performed by qualified personnel: (1) At least weekly for a minimum of four inspections per month; and (2) As often as is necessary to ensure that appropriate erosion and sediment controls have been properly constructed and maintained.
VerifiedMSR10 Permit, ACT6, S-5; ACT5, T-16Source
Who may inspect

A person knowledgeable in the principles and practice of erosion and sediment controls who possesses the skills to assess conditions at the construction site that could impact storm water quality and to assess the effectiveness of any sediment and erosion control measures.

Why this applies here: This is why Basinwise cannot perform your inspections. The permit requires a trained person physically on the site.

QUALIFIED PERSONNEL means a person knowledgeable in the principles and practice of erosion and sediment controls who possesses the skills to assess conditions at the construction site that could impact storm water quality and to assess the effectiveness of any sediment and erosion control measures selected to control the quality of storm water discharges from the construction activity.
VerifiedMSR10 Permit, ACT12, T-29Source

Stabilisation

Initiate stabilisation

Vegetative stabilization measures must be initiated whenever land-disturbing activities have ceased for 14 or more calendar days; 'immediately' means no later than the next work day.

Why this applies here: This applies at both land disturbance amounts.

Soil stabilization-vegetative stabilization measures must be initiated whenever any clearing, grading, grubbing, excavating or other land disturbing activities have temporarily or permanently ceased on any portion of the site and will not resume for a period of fourteen (14) calendar days or more.
VerifiedMSR10 Permit, ACT5, T-4Source

Corrective action

Corrective action, minor fix

As soon as possible, not to exceed 24 hours of the inspection (unless prevented by unsafe weather)

Any poorly functioning erosion controls or sediment controls, non-compliant discharges, or any other deficiencies observed during the inspections required under this permit shall be corrected as soon as possible, but not to exceed 24 hours of the inspection unless prevented by unsafe weather conditions as documented on the inspection form.
VerifiedMSR10 Permit, ACT5, T-16; ACT6, S-3(11)Source
Corrective action, major fix
5

Temporary containment within 24 hours, permanent corrective measures within 5 days of the inspection.

In the event of an unanticipated breach of a sediment basin/pond, temporary containment measures shall be taken within 24 hours after the inspection. Permanent corrective measures shall be implemented within five (5) days of the inspection.
VerifiedMSR10 Permit, ACT5, T-16Source

Buffers

Natural buffer
50

Provide and maintain a 50-foot undisturbed natural buffer around waters of the US, or a smaller buffer supplemented by equivalent controls.

Provide and maintain a 50-foot undisturbed natural buffer around waters of the United States; or provide and maintain an undisturbed natural buffer that is less than 50 feet and is supplemented by additional erosion and sediment controls which in combination achieves the sediment load reduction equivalent to a 50-foot undisturbed natural buffer.
VerifiedMSR10 Permit, ACT5, T-3(6)Source

Records you must keep

Corrective action log entries

MDEQ must be notified orally within 24 hours from the time noncompliance endangering health/environment is discovered.

The coverage recipient shall notify the MDEQ orally within twenty-four (24) hours from the time he or she becomes aware of unanticipated noncompliance, which may endanger health or the environment.
VerifiedMSR10 Permit, ACT11, T-17(2)Source
Record retention
3

All records, reports, forms and information resulting from activities required by this permit shall be retained for at least 3 years from the date generated.

Why this applies here: The clock runs from permit expiry or termination, not from when the record was written, so on a multi year project every record stays live for the whole project plus three years.

All records, reports, forms and information resulting from activities required by this permit shall be retained for a period of at least three (3) years from the date that the document(s) was generated.
VerifiedMSR10 Permit, ACT9, R-1Source

Screen a Mississippi site now

Your acreage, your receiving water, your answer. Runs in your browser, nothing is transmitted.

Screen your site

Runs in your browser

Total land disturbance over the whole project, including staging and access. This decides whether you need a permit at all.

Optional. If you phase the work, the most that will be disturbed at once. Leave blank if the whole site is open together. The stabilisation deadline turns on this figure, not the total.

A half acre lot inside a 40 acre subdivision is covered even though the lot alone is under the threshold. This is the most commonly missed trigger in the permit.

Receiving water and site conditions(optional, but they change the inspection frequency)

May allow a reduced inspection frequency during the seasonally dry period.

EPA keeps permitting authority in Indian country even inside a state that runs its own programme.

No account, no card, nothing transmitted.

What a plan has to cover, under the federal permit

This is EPA's list, from the 2022 Construction General Permit. It does NOT govern in Mississippi, where the state issues its own permit and sets its own contents. It is here as a shape to expect, not as the requirement you will be held to.

General SWPPP requirementPart 7.1Verified
  • All operators associated with a construction site under this permit must develop a SWPPP consistent with Part 7 prior to their submittal of the NOI. The SWPPP must be kept up-to-date throughout coverage under this permit. If a SWPPP was prepared under a previous version of this permit, the operator must review and update it before submitting an NOI.
All Site OperatorsPart 7.2.1Verified
  • Include a list of all other operators who will be engaged in construction activities at the site, and the areas of the site over which each operator has control.
Stormwater TeamPart 7.2.2Verified
  • Identify the personnel (by name and position) on the stormwater team pursuant to Part 6.1, their individual responsibilities, and which members are responsible for conducting inspections. Include verification that each member has received the Part 6.2 training, and documentation that inspection personnel have received the Part 6.3 training (EPA inspector training certificates, or documentation of a current non-EPA program certification plus confirmation the program satisfies the Part 6.3b minimum elements).
Nature of Construction ActivitiesParts 7.2.3a - 7.2.3iVerified
  • A description of the nature of your construction activities, including the age or dates of past renovations for structures undergoing demolition
  • The size of the property (in acres, or length in miles if a linear construction site)
  • The total area expected to be disturbed by the construction activities (to the nearest quarter acre, or nearest quarter mile if a linear construction site)
  • A description of any on-site and off-site construction support activity areas covered by this permit
  • The maximum area expected to be disturbed at any one time, including on-site and off-site construction support activity areas
  • A description and projected schedule for: commencement of construction activities in each portion of the site (clearing and grubbing, mass grading, demolition, site preparation, final grading, and creation of soil and vegetation stockpiles requiring stabilization); temporary or permanent cessation of construction activities in each portion; temporary or final stabilization of exposed areas for each portion; and removal of temporary stormwater controls and construction equipment or vehicles and cessation of construction-related pollutant-generating activities
  • A list and description of all pollutant-generating activities on the site, with an inventory of pollutants or pollutant constituents associated with each, taking into account where potential spills and leaks could occur and any known hazardous or toxic substances such as PCBs and asbestos that will be disturbed or removed
  • Business days and hours for the project
  • If conducting construction activities in response to a public emergency, a description of the cause of the emergency, information substantiating its occurrence (e.g. a State disaster declaration), and a description of the construction necessary to reestablish affected public services
Site MapParts 7.2.4a - 7.2.4kVerified
  • Boundaries of the property
  • Locations where construction activities will occur, including: locations of earth-disturbing activities (noting any phasing) including demolition; approximate slopes before and after major grading (noting any steep slopes); locations where sediment, soil or other construction materials will be stockpiled; any receiving water crossings; designated points where vehicles will exit onto paved roads; locations of structures and other impervious surfaces upon completion; and locations of on-site and off-site construction support activity areas
  • Locations of any receiving waters within the site and all receiving waters within one mile downstream of the site's discharge point(s), identifying whether any are listed as impaired or identified as a Tier 2, Tier 2.5 or Tier 3 water
  • Any areas of Federally listed critical habitat within the action area of the site
  • Type and extent of pre-construction cover on the site (e.g. vegetative cover, forest, pasture, pavement, structures)
  • Drainage patterns of stormwater and authorized non-stormwater before and after major grading activities
  • Stormwater and authorized non-stormwater discharge locations, including discharges to storm drain inlets (noting whether the inlet conveys stormwater to a sediment basin, sediment trap or similarly effective control), discharges directly to receiving waters, and locations where turbidity benchmark monitoring will take place
  • Locations of all potential pollutant-generating activities identified in Part 7.2.3g
  • Designated areas where construction wastes covered by the Part 2.3.3e.ii exception will be stored
  • Locations of stormwater controls, including natural buffer areas and any shared controls utilized to comply with this permit
  • Locations where polymers, flocculants or other treatment chemicals will be used and stored
Non-Stormwater DischargesPart 7.2.5Verified
  • Identify all authorized non-stormwater discharges in Part 1.2.2 that will or may occur.
Procedures for Inspection, Maintenance, and Corrective ActionParts 7.2.7a - 7.2.7eVerified
  • The inspection schedule you will follow, based on whether your site is subject to Part 4.2 or Part 4.3, or whether it qualifies for any of the reduced inspection frequencies in Part 4.4
  • If conducting inspections under Part 4.2.2, Part 4.3 or Part 4.4.1b, the location of the rain gauge or the address of the weather station you will use to obtain rainfall data
  • If reducing your inspection frequency in accordance with Part 4.4.1b, the beginning and ending dates of the seasonally defined arid period for your area or the valid period of drought
  • If reducing your inspection frequency in accordance with Part 4.4.3, the beginning and ending dates of frozen conditions on your site
  • Any maintenance or inspection checklists or other forms that will be used
Procedures for Turbidity Benchmark Monitoring from Dewatering Discharges (if applicable)Part 7.2.8Verified
  • If required to comply with the Part 3.3 turbidity benchmark monitoring requirements, describe the procedures you will follow to collect and evaluate samples, report results to EPA, keep records of monitoring information, and take corrective action when necessary. Include the specific type of turbidity meter you will use and any manuals or manufacturer instructions on how to operate and calibrate it. Describe any coordinating arrangement with other permitted operators on the same site, including which parties are tasked with specific responsibilities. If EPA has approved an alternate turbidity benchmark, include the data and documentation relied on to request it.
Compliance with Other RequirementsParts 7.2.9a - 7.2.9cVerified
  • Threatened and Endangered Species Protection: include the documentation required in the Endangered Species Protection section of the NOI in NeT, or the ESA worksheet in Appendix D, supporting your eligibility
  • Historic Properties: include the documentation required in Appendix E supporting your eligibility with regard to the protection of historic properties
  • Safe Drinking Water Act Underground Injection Control (UIC) requirements: if using infiltration trenches, commercially manufactured pre-cast or pre-built proprietary subsurface detention vaults/chambers/devices designed to capture and infiltrate stormwater, or drywells, seepage pits or improved sinkholes, document any contact with the applicable State agency or EPA Regional Office responsible for underground injection wells. Such controls would generally be considered Class V UIC wells
SWPPP CertificationPart 7.2.10Verified
  • Your signatory must sign and date your SWPPP in accordance with Appendix G, Part G.11.
Post-Authorization Additions to the SWPPPParts 7.2.11a - 7.2.11cVerified
  • A copy of your NOI submitted to EPA along with any correspondence exchanged between you and EPA related to coverage under this permit
  • A copy of the acknowledgment letter you receive from NeT assigning your NPDES ID (i.e. permit tracking number)
  • A copy of this permit (an electronic copy easily available to the stormwater team is also acceptable)

Read the permit itself at the source document.

What people ask about SWPPP requirements in Mississippi

What are the SWPPP requirements in Mississippi?

Mississippi issues its own construction general permit, and we have read Large Construction General Permit for Land Disturbing Activities of Five (5) or More Acres (MSR10). The requirements listed on this page, such as inspection frequency, who may inspect, stabilisation, corrective action and record retention, are cited to that permit rather than to EPA's. Anything we have not transcribed is left out instead of assumed to match the federal rule, and the scope note on this page says which sites the permit does not cover. Confirm the current permit and any site-size variant with Mississippi Department of Environmental Quality (MDEQ).

Who may prepare a SWPPP in Mississippi?

No preparer credential was found for Mississippi. On what we have verified, a generated plan can be adopted by the operator without a credentialed signature. Local ordinances can still be stricter than state law.

How often must a Mississippi site be inspected?

The inspection frequency is set by the Mississippi construction general permit, which we have not read. Confirm it with Mississippi Department of Environmental Quality (MDEQ).

Who may prepare a stormwater plan in Mississippi

The permit makes you keep the record, not just know the answer

Screening is free. Pro generates the site specific plan document and retains the inspection and corrective action log.