SWPPP requirements in Missouri

Missouri issues its own construction general permit. We have read Construction or Land Disturbance Master General Stormwater Permit, Permit Number MORA00000 and list below the requirements we could cite to it, with the scope limits stated plainly. Screen your own acreage further down.

Who may prepare the plan

No preparer credential found

No preparer credential was found for Missouri. On what we have verified, a generated plan can be adopted by the operator without a credentialed signature. Local ordinances can still be stricter than state law.

Missouri does not gate SWPPP preparation behind any specific certification, license, or professional credential — confirmed as an explicit absence in both the implementing regulation and MoDNR's public program materials. No PE stamp is required by the state permit program for the SWPPP itself (a City of Mexico, MO municipal grading/drainage plan review requires a licensed PE seal, but that is a local requirement layered on top, not a MORA00000 state-permit requirement). Preparers commonly hold voluntary industry credentials such as CPESC as best practice, but none is legally mandated. This conclusion rests on the regulation text and program pages, not a direct read of the full MORA00000 permit document, which is administered entirely through MoDNR's online ePermitting system and was inaccessible (HTTP 403) at every access attempt.

Verified10 CSR 20-6.200 (Missouri stormwater regulations); MoDNR Construction/Land Disturbance Permits program page (MORA00000)Source

Coverage trigger

Worked through at 3 acres

The project disturbs 3 acres, at or above the 1 acre threshold, so it needs permit coverage.

The trigger people miss is the second one. A half acre lot inside a 40 acre subdivision is covered, because the larger common plan of development or sale is what counts, not the lot.

Read these before you act on the answer

  • Requirements below are what we have read and cited directly from Construction or Land Disturbance Master General Stormwater Permit, Permit Number MORA00000, not the federal CGP. A category we have not yet transcribed from this permit is omitted here rather than assumed to match EPA's rule.
  • The permit number MO-R100007 originally supplied as known context does not correspond to the general permit private construction sites actually use -- MO-R100xxx ('Area-Wide Land Disturbance Stormwater General Permit') is issued only to governmental jurisdictions. The general permit individual private developers/contractors use is MO-RA00000 ('Land Disturbance Stormwater General Operating Permit'), confirmed via DNR's own program page. This dataset covers MO-RA00000. DNR's static document server still serves the PRIOR permit cycle text (HTTP-verified last-modified 2017-02-06, effective 2017-02-08, expired 2022-02-07) -- it was never updated after the 2022 renewal. DNR's overview page confirms 'The current permit expires Feb. 7, 2027' (a newer cycle exists) but its full operative text could not be located/fetched (DNR's water pages return HTTP 403 to automated fetches). All substantive figures below are verified against the 2017-2022 text -- the most recent full permit text obtainable -- not an independently confirmed 2022-2027 copy. The current cycle's effective date is not verified with a direct quote and is set to null. No federal-style acreage-tiered stabilization schedule, sensitive-waters increased-inspection rule, arid/semi-arid reduced-inspection rule, or fixed-day NOI/NOT deadline was found in the fetched text, so those canonical ids are omitted.
  • No preparer credential was found for Missouri. On what we have verified, a generated plan can be adopted by the operator without a credentialed signature. Local ordinances can still be stricter than state law.
  • Basinwise does not perform the physical site inspections the permit requires. Those must be carried out on site by a qualified person.

What the permit requires of a Missouri site

Worked for a three acre site with the receiving water unconfirmed. Each line says why it attached to this site rather than in general. Check the notes above for the site sizes this permit does not cover.

Filing

Plan before Notice of Intent

The SWPPP must be developed prior to issuance of the permit and must be specific to the land disturbance activities at the site; a Missouri State Operating Permit that specifically identifies the project must be issued before any site vegetation is removed or the site is disturbed.

The SWPPP must be developed prior to issuance of the permit and must be specific to the land disturbance activities at the site.
VerifiedMO-RA00000 permit, Applicability Section 1 and Requirements Section 6Source

Inspections

Inspection frequency, option 1
7

At least once every seven calendar days, and within 48 hours after any storm equal to or greater than a 2-year, 24-hour storm has ceased during a normal work day (within 72 hours if the storm ceases during a non-work day). This is one of two inspector-selectable schedules; the SWPPP must document which is used.

Why this applies here: You have not confirmed whether the site discharges to an impaired or high quality water. If it does, the increased frequency applies instead and this answer changes.

At least once every seven calendar days and within 48 hours after any storm equal to or greater than a 2-year, 24-hour storm has ceased during a normal work day and within 72 hours if the rain event ceases during a non-work day such as a weekend or holiday
VerifiedMO-RA00000 permit, Requirements Section 15.a (Site Inspections Reports)Source
Inspection frequency, option 2
14

Once every 14 calendar days, and within 24 hours of the occurrence of a storm event of 0.25 inches of precipitation or greater, or of runoff from snowmelt.

Why this applies here: You have not confirmed whether the site discharges to an impaired or high quality water. If it does, the increased frequency applies instead and this answer changes.

Once every 14 calendar days and within 24 hours of the occurrence of a storm event of 0.25 inches of precipitation or greater, or the occurrence of runoff from snowmelt.
VerifiedMO-RA00000 permit, Requirements Section 15.bSource
Who may inspect

These inspections shall be conducted by a qualified person, one who is responsible for environmental matters at the site, or a person trained by and directly supervised by the person responsible for environmental matters at the site.

Why this applies here: This is why Basinwise cannot perform your inspections. The permit requires a trained person physically on the site.

These inspections shall be conducted by a qualified person, one who is responsible for environmental matters at the site, or a person trained by and directly supervised by the person responsible for environmental matters at the site.
VerifiedMO-RA00000 permit, Requirements Section 15Source

Stabilisation

Initiate stabilisation

Immediately -- upon either temporary cessation of soil-disturbing activity on any portion of the site for a period expected to exceed 14 calendar days, or permanent cessation.

Why this applies here: This applies at both land disturbance amounts.

For soil disturbing activities that have temporarily ceased on any portion of the site and will not resume for a period exceeding 14 calendar days: ... Stabilization must be initiated immediately and completed within 14 calendar days.
VerifiedMO-RA00000 permit, Requirements Section 8.h (Disturbed Areas)Source

Corrective action

Corrective action, major fix
7

Any structural or maintenance problems noted during an inspection must be corrected as soon as possible but no more than seven calendar days after the inspection.

Any structural or maintenance problems shall be noted in an inspection report and corrected as soon as possible but no more than seven calendar days after the inspection.
VerifiedMO-RA00000 permit, Requirements Section 15Source

Buffers

Natural buffer
50

For surface waters of the state, the permittee must either provide/maintain a 50-foot undisturbed natural buffer, a smaller buffer supplemented by equivalent controls, or (if infeasible) controls achieving the equivalent sediment-load reduction.

Provide and maintain a 50-foot undisturbed natural buffer; Provide and maintain an undisturbed natural buffer that is less than 50 feet and is supplemented by erosion and sediment controls that achieve the sediment load reduction equivalent to a 50-foot undisturbed natural buffer; or If infeasible to provide and maintain an undisturbed natural buffer of any size, implement erosion and sediment controls to achieve the sediment load reduction equivalent to a 50-foot undisturbed natural buffer.
VerifiedMO-RA00000 permit, Requirements Section 8.fSource

Records you must keep

Record retention
3

The permittee must retain copies of the general permit, the SWPPP and all amendments, monitoring/analysis results, and all site inspection records for at least three years from the date of the Letter of Termination.

Why this applies here: The clock runs from permit expiry or termination, not from when the record was written, so on a multi year project every record stays live for the whole project plus three years.

The records shall be retained for a period of at least three years from the date of the Letter of Termination.
VerifiedMO-RA00000 permit, Records Section 1Source

Screen a Missouri site now

Your acreage, your receiving water, your answer. Runs in your browser, nothing is transmitted.

Screen your site

Runs in your browser

Total land disturbance over the whole project, including staging and access. This decides whether you need a permit at all.

Optional. If you phase the work, the most that will be disturbed at once. Leave blank if the whole site is open together. The stabilisation deadline turns on this figure, not the total.

A half acre lot inside a 40 acre subdivision is covered even though the lot alone is under the threshold. This is the most commonly missed trigger in the permit.

Receiving water and site conditions(optional, but they change the inspection frequency)

May allow a reduced inspection frequency during the seasonally dry period.

EPA keeps permitting authority in Indian country even inside a state that runs its own programme.

No account, no card, nothing transmitted.

What a plan has to cover, under the federal permit

This is EPA's list, from the 2022 Construction General Permit. It does NOT govern in Missouri, where the state issues its own permit and sets its own contents. It is here as a shape to expect, not as the requirement you will be held to.

General SWPPP requirementPart 7.1Verified
  • All operators associated with a construction site under this permit must develop a SWPPP consistent with Part 7 prior to their submittal of the NOI. The SWPPP must be kept up-to-date throughout coverage under this permit. If a SWPPP was prepared under a previous version of this permit, the operator must review and update it before submitting an NOI.
All Site OperatorsPart 7.2.1Verified
  • Include a list of all other operators who will be engaged in construction activities at the site, and the areas of the site over which each operator has control.
Stormwater TeamPart 7.2.2Verified
  • Identify the personnel (by name and position) on the stormwater team pursuant to Part 6.1, their individual responsibilities, and which members are responsible for conducting inspections. Include verification that each member has received the Part 6.2 training, and documentation that inspection personnel have received the Part 6.3 training (EPA inspector training certificates, or documentation of a current non-EPA program certification plus confirmation the program satisfies the Part 6.3b minimum elements).
Nature of Construction ActivitiesParts 7.2.3a - 7.2.3iVerified
  • A description of the nature of your construction activities, including the age or dates of past renovations for structures undergoing demolition
  • The size of the property (in acres, or length in miles if a linear construction site)
  • The total area expected to be disturbed by the construction activities (to the nearest quarter acre, or nearest quarter mile if a linear construction site)
  • A description of any on-site and off-site construction support activity areas covered by this permit
  • The maximum area expected to be disturbed at any one time, including on-site and off-site construction support activity areas
  • A description and projected schedule for: commencement of construction activities in each portion of the site (clearing and grubbing, mass grading, demolition, site preparation, final grading, and creation of soil and vegetation stockpiles requiring stabilization); temporary or permanent cessation of construction activities in each portion; temporary or final stabilization of exposed areas for each portion; and removal of temporary stormwater controls and construction equipment or vehicles and cessation of construction-related pollutant-generating activities
  • A list and description of all pollutant-generating activities on the site, with an inventory of pollutants or pollutant constituents associated with each, taking into account where potential spills and leaks could occur and any known hazardous or toxic substances such as PCBs and asbestos that will be disturbed or removed
  • Business days and hours for the project
  • If conducting construction activities in response to a public emergency, a description of the cause of the emergency, information substantiating its occurrence (e.g. a State disaster declaration), and a description of the construction necessary to reestablish affected public services
Site MapParts 7.2.4a - 7.2.4kVerified
  • Boundaries of the property
  • Locations where construction activities will occur, including: locations of earth-disturbing activities (noting any phasing) including demolition; approximate slopes before and after major grading (noting any steep slopes); locations where sediment, soil or other construction materials will be stockpiled; any receiving water crossings; designated points where vehicles will exit onto paved roads; locations of structures and other impervious surfaces upon completion; and locations of on-site and off-site construction support activity areas
  • Locations of any receiving waters within the site and all receiving waters within one mile downstream of the site's discharge point(s), identifying whether any are listed as impaired or identified as a Tier 2, Tier 2.5 or Tier 3 water
  • Any areas of Federally listed critical habitat within the action area of the site
  • Type and extent of pre-construction cover on the site (e.g. vegetative cover, forest, pasture, pavement, structures)
  • Drainage patterns of stormwater and authorized non-stormwater before and after major grading activities
  • Stormwater and authorized non-stormwater discharge locations, including discharges to storm drain inlets (noting whether the inlet conveys stormwater to a sediment basin, sediment trap or similarly effective control), discharges directly to receiving waters, and locations where turbidity benchmark monitoring will take place
  • Locations of all potential pollutant-generating activities identified in Part 7.2.3g
  • Designated areas where construction wastes covered by the Part 2.3.3e.ii exception will be stored
  • Locations of stormwater controls, including natural buffer areas and any shared controls utilized to comply with this permit
  • Locations where polymers, flocculants or other treatment chemicals will be used and stored
Non-Stormwater DischargesPart 7.2.5Verified
  • Identify all authorized non-stormwater discharges in Part 1.2.2 that will or may occur.
Procedures for Inspection, Maintenance, and Corrective ActionParts 7.2.7a - 7.2.7eVerified
  • The inspection schedule you will follow, based on whether your site is subject to Part 4.2 or Part 4.3, or whether it qualifies for any of the reduced inspection frequencies in Part 4.4
  • If conducting inspections under Part 4.2.2, Part 4.3 or Part 4.4.1b, the location of the rain gauge or the address of the weather station you will use to obtain rainfall data
  • If reducing your inspection frequency in accordance with Part 4.4.1b, the beginning and ending dates of the seasonally defined arid period for your area or the valid period of drought
  • If reducing your inspection frequency in accordance with Part 4.4.3, the beginning and ending dates of frozen conditions on your site
  • Any maintenance or inspection checklists or other forms that will be used
Procedures for Turbidity Benchmark Monitoring from Dewatering Discharges (if applicable)Part 7.2.8Verified
  • If required to comply with the Part 3.3 turbidity benchmark monitoring requirements, describe the procedures you will follow to collect and evaluate samples, report results to EPA, keep records of monitoring information, and take corrective action when necessary. Include the specific type of turbidity meter you will use and any manuals or manufacturer instructions on how to operate and calibrate it. Describe any coordinating arrangement with other permitted operators on the same site, including which parties are tasked with specific responsibilities. If EPA has approved an alternate turbidity benchmark, include the data and documentation relied on to request it.
Compliance with Other RequirementsParts 7.2.9a - 7.2.9cVerified
  • Threatened and Endangered Species Protection: include the documentation required in the Endangered Species Protection section of the NOI in NeT, or the ESA worksheet in Appendix D, supporting your eligibility
  • Historic Properties: include the documentation required in Appendix E supporting your eligibility with regard to the protection of historic properties
  • Safe Drinking Water Act Underground Injection Control (UIC) requirements: if using infiltration trenches, commercially manufactured pre-cast or pre-built proprietary subsurface detention vaults/chambers/devices designed to capture and infiltrate stormwater, or drywells, seepage pits or improved sinkholes, document any contact with the applicable State agency or EPA Regional Office responsible for underground injection wells. Such controls would generally be considered Class V UIC wells
SWPPP CertificationPart 7.2.10Verified
  • Your signatory must sign and date your SWPPP in accordance with Appendix G, Part G.11.
Post-Authorization Additions to the SWPPPParts 7.2.11a - 7.2.11cVerified
  • A copy of your NOI submitted to EPA along with any correspondence exchanged between you and EPA related to coverage under this permit
  • A copy of the acknowledgment letter you receive from NeT assigning your NPDES ID (i.e. permit tracking number)
  • A copy of this permit (an electronic copy easily available to the stormwater team is also acceptable)

Read the permit itself at the source document.

What people ask about SWPPP requirements in Missouri

What are the SWPPP requirements in Missouri?

Missouri issues its own construction general permit, and we have read Construction or Land Disturbance Master General Stormwater Permit, Permit Number MORA00000. The requirements listed on this page, such as inspection frequency, who may inspect, stabilisation, corrective action and record retention, are cited to that permit rather than to EPA's. Anything we have not transcribed is left out instead of assumed to match the federal rule, and the scope note on this page says which sites the permit does not cover. Confirm the current permit and any site-size variant with Missouri Department of Natural Resources (MoDNR), Water Protection Program, Division of Environmental Quality.

Who may prepare a SWPPP in Missouri?

No preparer credential was found for Missouri. On what we have verified, a generated plan can be adopted by the operator without a credentialed signature. Local ordinances can still be stricter than state law.

How often must a Missouri site be inspected?

The inspection frequency is set by the Missouri construction general permit, which we have not read. Confirm it with Missouri Department of Natural Resources (MoDNR), Water Protection Program, Division of Environmental Quality.

Who may prepare a stormwater plan in Missouri

The permit makes you keep the record, not just know the answer

Screening is free. Pro generates the site specific plan document and retains the inspection and corrective action log.