Plan before Notice of Intent
An SWP3 must be prepared prior to submission of an NOI.
An SWP3 must be prepared prior to submission of an NOI. The SWP3 must be kept up-to-date throughout coverage under this permit.
Oklahoma
Oklahoma issues its own construction general permit. We have read General Permit OKR10 for Stormwater Discharges from Construction Activities Within the State of Oklahoma and list below the requirements we could cite to it, with the scope limits stated plainly. Screen your own acreage further down.
Who may prepare the plan
No preparer credential foundNo preparer credential was found for Oklahoma. On what we have verified, a generated plan can be adopted by the operator without a credentialed signature. Local ordinances can still be stricter than state law.
The permit states it explicitly: use of a licensed PE for plan preparation is not required. OKR10 Part 5.1.B.
No permit section cited. Confirm this with your permitting authority.
Coverage trigger
The project disturbs 3 acres, at or above the 1 acre threshold, so it needs permit coverage.
The trigger people miss is the second one. A half acre lot inside a 40 acre subdivision is covered, because the larger common plan of development or sale is what counts, not the lot.
Worked for a three acre site with the receiving water unconfirmed. Each line says why it attached to this site rather than in general. Check the notes above for the site sizes this permit does not cover.
An SWP3 must be prepared prior to submission of an NOI.
An SWP3 must be prepared prior to submission of an NOI. The SWP3 must be kept up-to-date throughout coverage under this permit.
Submit an NOI at least 14 days prior to commencing construction activities.
Why this applies here: This is the deadline for a new site. A transfer to a new operator or an emergency related project has a different deadline.
Operators of new construction projects/activities that commence after the effective date of this permit must submit an NOI at least 14 days prior to commencing construction activities.
A complete NOT must be submitted within 30 days if a termination condition has been met.
A complete NOT (DEQ Form 606-003) must be submitted to DEQ within 30 days if one or more of the following conditions have been met
At a minimum, conduct a site inspection once every 14 calendar days and within 24 hours of the end of a storm event of 0.5 inches or greater.
Why this applies here: You have not confirmed whether the site discharges to an impaired or high quality water. If it does, the increased frequency applies instead and this answer changes.
At a minimum, you must conduct a site inspection once every 14 calendar days and within 24 hours of the end of a storm event of 0.5 inches or greater and within 24 hours of a discharge generated by snowmelt, unless you are discharging from a high priority site subject to Part 4.6.B.4.
Those who are knowledgeable in the principles and practice of erosion and sediment controls and pollution prevention, who possess the skills and training to assess conditions at the construction site that could impact stormwater quality.
Why this applies here: This is why Basinwise cannot perform your inspections. The permit requires a trained person physically on the site.
Qualified Person or Qualified Personnel means those (either the operator's employees or outside personnel) who are knowledgeable in the principles and practice of erosion and sediment controls and pollution prevention, who possess the skills and training to assess conditions at the construction site that could impact stormwater quality.
Initiate the installation of stabilization measures immediately in any disturbed areas where construction activities have permanently ceased or will be temporarily inactive for 14 or more calendar days.
Why this applies here: This applies at both land disturbance amounts.
Initiate the installation of stabilization measures immediately in any disturbed areas on any portion of the site where construction activities have permanently ceased or will be temporarily inactive for 14 or more calendar days.
Install a new or modified control and make it operational, or complete the repair, by no later than 7 calendar days from the time of discovery.
You must install a new or modified control and make it operational, or complete the repair, by no later than seven calendar days from the time of discovery.
Maintain a natural buffer zone of at least 50 feet between disturbed areas and perennial/intermittent streams, creeks, rivers, lakes, ephemeral streams, or drainages.
When any waters of the state are located on or immediately adjacent to the site... you must maintain a natural buffer zone or equivalent erosion and sediment controls... The minimum width of the buffer is outlined in Table 4-1.
Complete an inspection report within 24 hours of completing any site inspection.
You must complete an inspection report within 24 hours of completing any site inspection.
Within 24 hours of discovering a corrective-action triggering condition, provide a record of the condition and how it was identified.
Within 24 hours of discovering the occurrence of one of the triggering conditions in Part 5.5.A.1 at your site, you must provide a record of the following: a. Which triggering condition was identified at your site.
Retain SWP3, all reports, and NOI data for at least 3 years from the date the site is finally stabilized.
Why this applies here: The clock runs from permit expiry or termination, not from when the record was written, so on a multi year project every record stays live for the whole project plus three years.
The permittee shall retain copies of the SWP3 and all reports required by this permit, and records of all data used to complete the NOI to be covered by this permit, for a period of at least three years from the date that the site is finally stabilized.
Your acreage, your receiving water, your answer. Runs in your browser, nothing is transmitted.
This is EPA's list, from the 2022 Construction General Permit. It does NOT govern in Oklahoma, where the state issues its own permit and sets its own contents. It is here as a shape to expect, not as the requirement you will be held to.
Read the permit itself at the source document.
Oklahoma issues its own construction general permit, and we have read General Permit OKR10 for Stormwater Discharges from Construction Activities Within the State of Oklahoma. The requirements listed on this page, such as inspection frequency, who may inspect, stabilisation, corrective action and record retention, are cited to that permit rather than to EPA's. Anything we have not transcribed is left out instead of assumed to match the federal rule, and the scope note on this page says which sites the permit does not cover. Confirm the current permit and any site-size variant with Oklahoma Department of Environmental Quality (Oklahoma DEQ).
No preparer credential was found for Oklahoma. On what we have verified, a generated plan can be adopted by the operator without a credentialed signature. Local ordinances can still be stricter than state law.
The inspection frequency is set by the Oklahoma construction general permit, which we have not read. Confirm it with Oklahoma Department of Environmental Quality (Oklahoma DEQ).
Screening is free. Pro generates the site specific plan document and retains the inspection and corrective action log.