SWPPP requirements in Utah

Utah issues its own construction general permit. We have read General Permit for Storm Water Discharges from Construction Activities (Construction General Permit), UPDES Permit No. UTRC00000 and list below the requirements we could cite to it, with the scope limits stated plainly. Screen your own acreage further down.

Who may prepare the plan

Conditional, depends on the site

Utah gates plan preparation only above a threshold this site does not meet. The gate applies above 5 acres. This site is 3 acres. On what we have verified, a generated plan can be adopted without a credentialed signature.

Qualifying routes

  • Utah Registered SWPPP Writer (RSW)
  • Licensed Professional Engineer (PE) in a related field
  • Professional Geologist (PG)
  • Certified Professional in Erosion and Sediment Control (CPESC)
  • Certified Professional in Storm Water Quality (CPSWQ)
  • National Institute for Certification in Engineering Technologies (NICET), Erosion and Sediment Control, Level 3

The gate is not a flat 5-acre cutoff: Part 7.2 requires a qualified SWPPP writer for any project disturbing more than 5 acres, AND for small (1-5 acre) projects that have a perennial surface water within 50 feet or a steep slope (70% or 35 degrees or more, with 10+ feet of elevation change). Below that threshold, no certified preparer is required at all. A PE stamp is explicitly not required by itself — a licensed PE (or PG) is one of five interchangeable acceptable qualifications alongside RSW, CPESC, CPSWQ and NICET Level 3, commonly overstated as mandatory. Verified against the permit's Part 7.2 text and independently cross-checked against a March 2026 official SWPPP compliance-evaluation checklist for the current permit, which cites identical section numbers and triggers.

VerifiedUtah Construction General Permit (UTRC00000), Part 7.2 "SWPPP Writer/Reviewer Certification Requirement" and Part 7.2.1.a-eSource

Coverage trigger

Worked through at 3 acres

The project disturbs 3 acres, at or above the 1 acre threshold, so it needs permit coverage.

The trigger people miss is the second one. A half acre lot inside a 40 acre subdivision is covered, because the larger common plan of development or sale is what counts, not the lot.

Read these before you act on the answer

  • Requirements below are what we have read and cited directly from General Permit for Storm Water Discharges from Construction Activities (Construction General Permit), UPDES Permit No. UTRC00000, not the federal CGP. A category we have not yet transcribed from this permit is omitted here rather than assumed to match EPA's rule.
  • No numeric effluent limits/benchmarks were found in the permit body for standard sites -- like the federal 2022 CGP, this UT permit relies on narrative technology-based requirements. No explicit fixed-day NOI-before-commencement deadline was found in Part 1.4, so deadline.noi.newSite is omitted rather than guessed. Utah's stabilization deadlines are day-count based (not acreage-tiered like federal Table 2), so a state.ut id was created instead.
  • Utah gates plan preparation only above a threshold this site does not meet. The gate applies above 5 acres. This site is 3 acres. On what we have verified, a generated plan can be adopted without a credentialed signature.
  • Basinwise does not perform the physical site inspections the permit requires. Those must be carried out on site by a qualified person.

What the permit requires of a Utah site

Worked for a three acre site with the receiving water unconfirmed. Each line says why it attached to this site rather than in general. Check the notes above for the site sizes this permit does not cover.

Filing

Plan before Notice of Intent

All operators must develop a SWPPP consistent with Part 7 prior to submitting the NOI, and keep it up-to-date throughout coverage.

All operators associated with a construction site under this Permit must develop a SWPPP consistent with the requirements in Part 7 prior to their submittal of the NOI.
VerifiedUPDES CGP UTRC00000, Part 7.1Source
Notice of Termination deadline
30

Submit a NOT within 30 calendar days after any Part 8.2 termination condition occurs.

You must submit a NOT within 30 calendar days after any one of the conditions in Part 8.2 occurs.
VerifiedUPDES CGP UTRC00000, Part 8.4Source

Inspections

Inspection frequency, option 1
7

At least once every seven (7) calendar days.

Why this applies here: You have not confirmed whether the site discharges to an impaired or high quality water. If it does, the increased frequency applies instead and this answer changes.

At least once every seven (7) calendar days; or
VerifiedUPDES CGP UTRC00000, Part 4.2.1Source
Inspection frequency, option 2
14

Once every 14 calendar days and within 24 hours of a storm event producing 0.5 inches or more of rain within 24 hours, or snowmelt runoff sufficient to cause a discharge.

Why this applies here: You have not confirmed whether the site discharges to an impaired or high quality water. If it does, the increased frequency applies instead and this answer changes.

Once every 14 calendar days and within 24 hours of the occurrence of: a. A storm event that produces 0.50 inches or more of rain within a 24-hour period. ... b. Runoff from snowmelt sufficient to cause a discharge.
VerifiedUPDES CGP UTRC00000, Part 4.2.2Source
Who may inspect

A qualified person is someone who has completed the training required by Part 6.3, which requires either a training program covering erosion/sediment control principles (e.g., Utah RSI, CPESC, CPSWQ, CESSWI, CISEC, NICET, UDOT ECS, CSI-Construction, QCIS, or EPA CGP Inspector Training) or a current valid construction inspection certification.

Why this applies here: This is why Basinwise cannot perform your inspections. The permit requires a trained person physically on the site.

A qualified person is someone who has completed the training required by Part 6.3.
VerifiedUPDES CGP UTRC00000, Parts 4.1 and 6.3Source

Stabilisation

Initiate stabilisation

Initiate stabilization measures in exposed-soil areas where activity has permanently ceased or will be temporarily inactive for 30+ calendar days, as soon as possible and prior to the end of the 30th day.

Why this applies here: This applies at both land disturbance amounts.

Initiate the installation of stabilization measures in any areas of exposed soil where construction activities have permanently ceased or will be temporarily inactive for 30 or more calendar days as soon as possible and prior to the end of the 30th day of inactivity.
VerifiedUPDES CGP UTRC00000, Part 2.2.14.a(1)Source

Corrective action

Corrective action, minor fix

close of the next business day

When the problem does not require a new or replacement control or significant repair, you must complete the corrective action by the close of the next business day.
VerifiedUPDES CGP UTRC00000, Part 5.2.2Source
Corrective action, major fix
7

Install the new or modified control and make it operational, or complete the repair, by no later than 7 calendar days from discovery.

When the problem requires a new or replacement control or significant repair, install the new or modified control and make it operational, or complete the repair, by no later than seven (7) calendar days from the time of discovery.
VerifiedUPDES CGP UTRC00000, Part 5.2.3Source

Buffers

Natural buffer
50

Provide and maintain natural buffers and/or equivalent erosion and sediment controls for discharges within 50 feet of the site's earth disturbances.

Provide and maintain natural buffers and/or equivalent erosion and sediment controls for discharges to waters of the state that are located within 50 feet of the site's earth disturbances.
VerifiedUPDES CGP UTRC00000, Part 2.2.1 and Appendix A.1-A.2.1Source

Records you must keep

Inspection report deadline
24

Complete an inspection report within 24 hours of completing any site inspection.

You must complete an inspection report within 24 hours of completing any site inspection.
VerifiedUPDES CGP UTRC00000, Part 4.7.1Source
Corrective action log entries

Within 24 hours of identifying the corrective action condition, document the specific condition and when you identified it.

Within 24 hours of identifying the corrective action condition, document the specific condition and the date and time you identified it.
VerifiedUPDES CGP UTRC00000, Part 5.4.1.aSource
Record retention
3

Retain inspection reports and corrective action logs for at least 3 years from the date permit coverage expires or terminates.

Why this applies here: The clock runs from permit expiry or termination, not from when the record was written, so on a multi year project every record stays live for the whole project plus three years.

You must retain all inspection reports completed for this Part for at least three (3) years from the date that your Permit coverage expires or you terminate coverage.
VerifiedUPDES CGP UTRC00000, Parts 4.7.4 and 5.4.5Source

Screen a Utah site now

Your acreage, your receiving water, your answer. Runs in your browser, nothing is transmitted.

Screen your site

Runs in your browser

Total land disturbance over the whole project, including staging and access. This decides whether you need a permit at all.

Optional. If you phase the work, the most that will be disturbed at once. Leave blank if the whole site is open together. The stabilisation deadline turns on this figure, not the total.

A half acre lot inside a 40 acre subdivision is covered even though the lot alone is under the threshold. This is the most commonly missed trigger in the permit.

Receiving water and site conditions(optional, but they change the inspection frequency)

May allow a reduced inspection frequency during the seasonally dry period.

EPA keeps permitting authority in Indian country even inside a state that runs its own programme.

No account, no card, nothing transmitted.

What a plan has to cover, under the federal permit

This is EPA's list, from the 2022 Construction General Permit. It does NOT govern in Utah, where the state issues its own permit and sets its own contents. It is here as a shape to expect, not as the requirement you will be held to.

General SWPPP requirementPart 7.1Verified
  • All operators associated with a construction site under this permit must develop a SWPPP consistent with Part 7 prior to their submittal of the NOI. The SWPPP must be kept up-to-date throughout coverage under this permit. If a SWPPP was prepared under a previous version of this permit, the operator must review and update it before submitting an NOI.
All Site OperatorsPart 7.2.1Verified
  • Include a list of all other operators who will be engaged in construction activities at the site, and the areas of the site over which each operator has control.
Stormwater TeamPart 7.2.2Verified
  • Identify the personnel (by name and position) on the stormwater team pursuant to Part 6.1, their individual responsibilities, and which members are responsible for conducting inspections. Include verification that each member has received the Part 6.2 training, and documentation that inspection personnel have received the Part 6.3 training (EPA inspector training certificates, or documentation of a current non-EPA program certification plus confirmation the program satisfies the Part 6.3b minimum elements).
Nature of Construction ActivitiesParts 7.2.3a - 7.2.3iVerified
  • A description of the nature of your construction activities, including the age or dates of past renovations for structures undergoing demolition
  • The size of the property (in acres, or length in miles if a linear construction site)
  • The total area expected to be disturbed by the construction activities (to the nearest quarter acre, or nearest quarter mile if a linear construction site)
  • A description of any on-site and off-site construction support activity areas covered by this permit
  • The maximum area expected to be disturbed at any one time, including on-site and off-site construction support activity areas
  • A description and projected schedule for: commencement of construction activities in each portion of the site (clearing and grubbing, mass grading, demolition, site preparation, final grading, and creation of soil and vegetation stockpiles requiring stabilization); temporary or permanent cessation of construction activities in each portion; temporary or final stabilization of exposed areas for each portion; and removal of temporary stormwater controls and construction equipment or vehicles and cessation of construction-related pollutant-generating activities
  • A list and description of all pollutant-generating activities on the site, with an inventory of pollutants or pollutant constituents associated with each, taking into account where potential spills and leaks could occur and any known hazardous or toxic substances such as PCBs and asbestos that will be disturbed or removed
  • Business days and hours for the project
  • If conducting construction activities in response to a public emergency, a description of the cause of the emergency, information substantiating its occurrence (e.g. a State disaster declaration), and a description of the construction necessary to reestablish affected public services
Site MapParts 7.2.4a - 7.2.4kVerified
  • Boundaries of the property
  • Locations where construction activities will occur, including: locations of earth-disturbing activities (noting any phasing) including demolition; approximate slopes before and after major grading (noting any steep slopes); locations where sediment, soil or other construction materials will be stockpiled; any receiving water crossings; designated points where vehicles will exit onto paved roads; locations of structures and other impervious surfaces upon completion; and locations of on-site and off-site construction support activity areas
  • Locations of any receiving waters within the site and all receiving waters within one mile downstream of the site's discharge point(s), identifying whether any are listed as impaired or identified as a Tier 2, Tier 2.5 or Tier 3 water
  • Any areas of Federally listed critical habitat within the action area of the site
  • Type and extent of pre-construction cover on the site (e.g. vegetative cover, forest, pasture, pavement, structures)
  • Drainage patterns of stormwater and authorized non-stormwater before and after major grading activities
  • Stormwater and authorized non-stormwater discharge locations, including discharges to storm drain inlets (noting whether the inlet conveys stormwater to a sediment basin, sediment trap or similarly effective control), discharges directly to receiving waters, and locations where turbidity benchmark monitoring will take place
  • Locations of all potential pollutant-generating activities identified in Part 7.2.3g
  • Designated areas where construction wastes covered by the Part 2.3.3e.ii exception will be stored
  • Locations of stormwater controls, including natural buffer areas and any shared controls utilized to comply with this permit
  • Locations where polymers, flocculants or other treatment chemicals will be used and stored
Non-Stormwater DischargesPart 7.2.5Verified
  • Identify all authorized non-stormwater discharges in Part 1.2.2 that will or may occur.
Procedures for Inspection, Maintenance, and Corrective ActionParts 7.2.7a - 7.2.7eVerified
  • The inspection schedule you will follow, based on whether your site is subject to Part 4.2 or Part 4.3, or whether it qualifies for any of the reduced inspection frequencies in Part 4.4
  • If conducting inspections under Part 4.2.2, Part 4.3 or Part 4.4.1b, the location of the rain gauge or the address of the weather station you will use to obtain rainfall data
  • If reducing your inspection frequency in accordance with Part 4.4.1b, the beginning and ending dates of the seasonally defined arid period for your area or the valid period of drought
  • If reducing your inspection frequency in accordance with Part 4.4.3, the beginning and ending dates of frozen conditions on your site
  • Any maintenance or inspection checklists or other forms that will be used
Procedures for Turbidity Benchmark Monitoring from Dewatering Discharges (if applicable)Part 7.2.8Verified
  • If required to comply with the Part 3.3 turbidity benchmark monitoring requirements, describe the procedures you will follow to collect and evaluate samples, report results to EPA, keep records of monitoring information, and take corrective action when necessary. Include the specific type of turbidity meter you will use and any manuals or manufacturer instructions on how to operate and calibrate it. Describe any coordinating arrangement with other permitted operators on the same site, including which parties are tasked with specific responsibilities. If EPA has approved an alternate turbidity benchmark, include the data and documentation relied on to request it.
Compliance with Other RequirementsParts 7.2.9a - 7.2.9cVerified
  • Threatened and Endangered Species Protection: include the documentation required in the Endangered Species Protection section of the NOI in NeT, or the ESA worksheet in Appendix D, supporting your eligibility
  • Historic Properties: include the documentation required in Appendix E supporting your eligibility with regard to the protection of historic properties
  • Safe Drinking Water Act Underground Injection Control (UIC) requirements: if using infiltration trenches, commercially manufactured pre-cast or pre-built proprietary subsurface detention vaults/chambers/devices designed to capture and infiltrate stormwater, or drywells, seepage pits or improved sinkholes, document any contact with the applicable State agency or EPA Regional Office responsible for underground injection wells. Such controls would generally be considered Class V UIC wells
SWPPP CertificationPart 7.2.10Verified
  • Your signatory must sign and date your SWPPP in accordance with Appendix G, Part G.11.
Post-Authorization Additions to the SWPPPParts 7.2.11a - 7.2.11cVerified
  • A copy of your NOI submitted to EPA along with any correspondence exchanged between you and EPA related to coverage under this permit
  • A copy of the acknowledgment letter you receive from NeT assigning your NPDES ID (i.e. permit tracking number)
  • A copy of this permit (an electronic copy easily available to the stormwater team is also acceptable)

Read the permit itself at the source document.

What people ask about SWPPP requirements in Utah

What are the SWPPP requirements in Utah?

Utah issues its own construction general permit, and we have read General Permit for Storm Water Discharges from Construction Activities (Construction General Permit), UPDES Permit No. UTRC00000. The requirements listed on this page, such as inspection frequency, who may inspect, stabilisation, corrective action and record retention, are cited to that permit rather than to EPA's. Anything we have not transcribed is left out instead of assumed to match the federal rule, and the scope note on this page says which sites the permit does not cover. Confirm the current permit and any site-size variant with Utah Department of Environmental Quality (Utah DEQ), Division of Water Quality.

Who may prepare a SWPPP in Utah?

Utah gates plan preparation only above a threshold this site does not meet. The gate applies above 5 acres. This site is 3 acres. On what we have verified, a generated plan can be adopted without a credentialed signature.

How often must a Utah site be inspected?

The inspection frequency is set by the Utah construction general permit, which we have not read. Confirm it with Utah Department of Environmental Quality (Utah DEQ), Division of Water Quality.

Who may prepare a stormwater plan in Utah

The permit makes you keep the record, not just know the answer

Screening is free. Pro generates the site specific plan document and retains the inspection and corrective action log.