Vermont
Who may prepare a stormwater plan in Vermont
Vermont requires a credentialed preparer only in some cases. Plan scope rather than acreage: Moderate risk projects only, per Appendix A's Risk Evaluation questionnaire: Overall Risk Score 1 or less = Low Risk (Site Drawing under the Low Risk Site Handbook, no stated preparer credential); Overall Risk Score 2 to 4 = Moderate Risk (site-specific EPSC Plan, Subpart 3.2 credential applies); Overall Risk Score 5 or higher, or 5+ acres concurrent earth disturbance, or a 14+ day stabilization schedule = ineligible for the general permit, requires an Individual Discharge Permit.
The answer
ConditionalVermont requires a credentialed preparer only in some cases. Plan scope rather than acreage: Moderate risk projects only, per Appendix A's Risk Evaluation questionnaire: Overall Risk Score 1 or less = Low Risk (Site Drawing under the Low Risk Site Handbook, no stated preparer credential); Overall Risk Score 2 to 4 = Moderate Risk (site-specific EPSC Plan, Subpart 3.2 credential applies); Overall Risk Score 5 or higher, or 5+ acres concurrent earth disturbance, or a 14+ day stabilization schedule = ineligible for the general permit, requires an Individual Discharge Permit.
What triggers it: Plan scope rather than acreage: Moderate risk projects only, per Appendix A's Risk Evaluation questionnaire: Overall Risk Score 1 or less = Low Risk (Site Drawing under the Low Risk Site Handbook, no stated preparer credential); Overall Risk Score 2 to 4 = Moderate Risk (site-specific EPSC Plan, Subpart 3.2 credential applies); Overall Risk Score 5 or higher, or 5+ acres concurrent earth disturbance, or a 14+ day stabilization schedule = ineligible for the general permit, requires an Individual Discharge Permit.
Credentials that qualify
- Certified engineer (required for moderate risk projects; the term 'certified engineer' is not defined anywhere in the permit, including its Appendix C definitions)
Confirmed by direct read of the permit. Subpart 3.2 verbatim: 'This Subpart, applicable to moderate risk construction activities, describes the required EPSC Plan that is to be prepared by a certified engineer and meet all requirements of the APPENDIX B.' Risk tiering is not acreage-based alone; it runs through Appendix A's questionnaire (eligibility screening, then a Basic and Detailed Risk Evaluation combining into an Overall Risk Score). 'Certified engineer' is genuinely undefined: the phrase appears exactly once in the 77-page permit, does not recur in Appendix C Definitions, and the terms 'professional engineer,' 'PE,' 'stamp,' 'seal' and 'licensed' do not appear anywhere. Vermont's engineering licensure statute (26 V.S.A. Chapter 20) only formally recognizes 'Professional Engineer' and 'Engineer Intern' — 'certified engineer' is not a defined credential under Vermont law either, so the ambiguity cannot be resolved by cross-referencing state licensure statute. Because the permit itself never invokes a stamp, seal or PE license, peStamp is left null rather than inferred as true.
What this means for a generated plan
Where a credential applies, or where we cannot confirm that none does, treat a generated document as a complete draft for a credentialed preparer to review, amend and sign. It is not by itself a compliant filed plan, and ours says so on its face.
Screen a Vermont site, credential answer included
What people ask about preparing a SWPPP in Vermont
Do I need a qualified preparer for a SWPPP in Vermont?
Vermont requires a credentialed preparer only in some cases. Plan scope rather than acreage: Moderate risk projects only, per Appendix A's Risk Evaluation questionnaire: Overall Risk Score 1 or less = Low Risk (Site Drawing under the Low Risk Site Handbook, no stated preparer credential); Overall Risk Score 2 to 4 = Moderate Risk (site-specific EPSC Plan, Subpart 3.2 credential applies); Overall Risk Score 5 or higher, or 5+ acres concurrent earth disturbance, or a 14+ day stabilization schedule = ineligible for the general permit, requires an Individual Discharge Permit.
Does a professional engineer have to stamp the plan in Vermont?
Practice act citations are routinely overstated on this point. A PE stamp is not required as a general matter in most states with no preparer gate, and where we have not verified it we will not assert either answer. Confirm with the state board or the permitting authority.