Plan before Notice of Intent
prepared and submitted together with the NOI (Moderate Risk only)
An EPSC Plan shall be prepared and submitted with the NOI for a moderate risk construction activity.
Vermont
Vermont issues its own construction general permit. We have read General Permit 3-9020 for Stormwater Runoff from Construction Sites and list below the requirements we could cite to it, with the scope limits stated plainly. Screen your own acreage further down.
Who may prepare the plan
Conditional, depends on the siteVermont gates plan preparation conditionally. The gate is triggered by plan scope rather than acreage: Moderate risk projects only, per Appendix A's Risk Evaluation questionnaire: Overall Risk Score 1 or less = Low Risk (Site Drawing under the Low Risk Site Handbook, no stated preparer credential); Overall Risk Score 2 to 4 = Moderate Risk (site-specific EPSC Plan, Subpart 3.2 credential applies); Overall Risk Score 5 or higher, or 5+ acres concurrent earth disturbance, or a 14+ day stabilization schedule = ineligible for the general permit, requires an Individual Discharge Permit. Confirm which case applies to your plan before relying on a generated document.
Qualifying routes
Confirmed by direct read of the permit. Subpart 3.2 verbatim: 'This Subpart, applicable to moderate risk construction activities, describes the required EPSC Plan that is to be prepared by a certified engineer and meet all requirements of the APPENDIX B.' Risk tiering is not acreage-based alone; it runs through Appendix A's questionnaire (eligibility screening, then a Basic and Detailed Risk Evaluation combining into an Overall Risk Score). 'Certified engineer' is genuinely undefined: the phrase appears exactly once in the 77-page permit, does not recur in Appendix C Definitions, and the terms 'professional engineer,' 'PE,' 'stamp,' 'seal' and 'licensed' do not appear anywhere. Vermont's engineering licensure statute (26 V.S.A. Chapter 20) only formally recognizes 'Professional Engineer' and 'Engineer Intern' — 'certified engineer' is not a defined credential under Vermont law either, so the ambiguity cannot be resolved by cross-referencing state licensure statute. Because the permit itself never invokes a stamp, seal or PE license, peStamp is left null rather than inferred as true.
Coverage trigger
The project disturbs 3 acres, at or above the 1 acre threshold, so it needs permit coverage.
The trigger people miss is the second one. A half acre lot inside a 40 acre subdivision is covered, because the larger common plan of development or sale is what counts, not the lot.
Worked for a three acre site with the receiving water unconfirmed. Each line says why it attached to this site rather than in general. Check the notes above for the site sizes this permit does not cover.
prepared and submitted together with the NOI (Moderate Risk only)
An EPSC Plan shall be prepared and submitted with the NOI for a moderate risk construction activity.
Submit before commencing construction activities; the exact lead time is not recorded for this id.
Why this applies here: This is the deadline for a new site. A transfer to a new operator or an emergency related project has a different deadline.
Construction activity shall not commence until an authorization to discharge is issued pursuant to this permit or an individual construction stormwater permit is issued.
At least once every 7 calendar days.
Why this applies here: You have not confirmed whether the site discharges to an impaired or high quality water. If it does, the increased frequency applies instead and this answer changes.
Inspections shall be conducted at least once every seven calendar days, immediately before any stormwater runoff producing event, and as required in Subpart 3.3.3.A.
On-Site Plan Coordinator (OSPC), knowledgeable in erosion prevention and sediment control principles/practice
Why this applies here: This is why Basinwise cannot perform your inspections. The permit requires a trained person physically on the site.
Such person shall be knowledgeable in the principles and practice of erosion prevention and sediment control and possess the skills and training to assess conditions at the construction site that could impact stormwater quality.
Confirm the exact minor-fix deadline against the cited permit section.
If site inspections ... identify BMPs that are not operating effectively, maintenance shall be performed as soon as possible and before the next storm event or melt event.
Confirm the exact major-fix deadline against the cited permit section.
the permittee shall modify the BMPs and EPSC Plan as necessary or as directed to include additional or modified BMPs designed to correct the problems identified. Revisions to the BMPs and EPSC Plan shall be completed and implemented within 72 hours following the inspection or investigation.
Provide and maintain a natural buffer or equivalent erosion and sediment controls near surface waters; the exact distance is not recorded for this id.
Will the proposed project have earth disturbance within 50 ft. (horizontal) upslope of any lake, pond, wetland, river, or stream? ... Will the project have any stormwater discharges from the construction site to receiving water(s) that do not first filter through a 50-ft. vegetated buffer?
Complete the inspection report within 24 hours of completing the site inspection.
If ... a discharge of visibly discolored stormwater from the construction site to waters of the State is observed, the permittee shall notify DEC by submitting a Discharge Report within 24 hours of discovering the discharge.
Document the condition and its completion; the exact documentation deadline is not recorded for this id.
if a certification of compliance cannot be provided at the time of inspection, the inspection report shall specifically identify non-compliance with the EPSC Plan and provide a schedule and corrective actions required for achieving full compliance.
Retain inspection reports and the corrective action log for at least 5 years from the date permit coverage expires or is terminated.
Why this applies here: The clock runs from permit expiry or termination, not from when the record was written, so on a multi year project every record stays live for the whole project plus three years.
The permittee shall retain records of all monitoring information ... copies of all reports required by this permit, and records of all data used to complete the application for this permit for a period of at least five years from the date of the sample, measurement, report, or application.
Your acreage, your receiving water, your answer. Runs in your browser, nothing is transmitted.
This is EPA's list, from the 2022 Construction General Permit. It does NOT govern in Vermont, where the state issues its own permit and sets its own contents. It is here as a shape to expect, not as the requirement you will be held to.
Read the permit itself at the source document.
Vermont issues its own construction general permit, and we have read General Permit 3-9020 for Stormwater Runoff from Construction Sites. The requirements listed on this page, such as inspection frequency, who may inspect, stabilisation, corrective action and record retention, are cited to that permit rather than to EPA's. Anything we have not transcribed is left out instead of assumed to match the federal rule, and the scope note on this page says which sites the permit does not cover. Confirm the current permit and any site-size variant with Vermont Agency of Natural Resources (ANR), Department of Environmental Conservation (DEC), Watershed Management Division.
Vermont gates plan preparation conditionally. The gate is triggered by plan scope rather than acreage: Moderate risk projects only, per Appendix A's Risk Evaluation questionnaire: Overall Risk Score 1 or less = Low Risk (Site Drawing under the Low Risk Site Handbook, no stated preparer credential); Overall Risk Score 2 to 4 = Moderate Risk (site-specific EPSC Plan, Subpart 3.2 credential applies); Overall Risk Score 5 or higher, or 5+ acres concurrent earth disturbance, or a 14+ day stabilization schedule = ineligible for the general permit, requires an Individual Discharge Permit. Confirm which case applies to your plan before relying on a generated document.
The inspection frequency is set by the Vermont construction general permit, which we have not read. Confirm it with Vermont Agency of Natural Resources (ANR), Department of Environmental Conservation (DEC), Watershed Management Division.
Screening is free. Pro generates the site specific plan document and retains the inspection and corrective action log.