Kansas
The stormwater permit for construction in Kansas
Kansas runs its own NPDES programme, so a state issued construction general permit governs. Below is what our engine can say about it, and where we have not read that permit, what it will not say.
Governing permit
Kansas Water Pollution Control General Permit and Authorization to Discharge, Stormwater Runoff from Construction Activities Under the National Pollutant Discharge Elimination System (General Permit No. S-MCST-2208-1, Federal Permit No. KSR100000)
- Issued by
- Kansas Department of Health and Environment (KDHE), Bureau of Water
- Permit number
- KSR100000
- Version determined against
- as published by the state agency
- Effective
- 2022-08-01
- Expires
- 2027-07-31
Who may prepare the plan
A credentialed preparer is requiredKansas requires a credentialed preparer. Treat the generated document as a complete draft for that person to review, adopt and sign. It is not by itself a compliant filed plan.
Qualifying routes
- Kansas-licensed Professional Engineer (PE)
- Kansas-licensed geologist
- Kansas-licensed architect
- Kansas-licensed landscape architect
- Certified Professional in Erosion and Sediment Control (CPESC)
Every SWP2 (SWPPP) covered by this permit must be developed and prepared under the supervision of one of: a licensed Kansas PE, geologist, architect, landscape architect, or a CPESC — no acreage-based exemption or tiering exists in the permit text, so this applies uniformly to all sites the permit covers. A PE stamp is not independently required — PE licensure is only one of five equally valid qualifying routes. Part 6.1 separately allows continued use of the prior permit's SWP2 Plan for up to 18 months after this permit's effective date before this credential requirement kicks in for any modification.
Does a site in Kansas need coverage
Worked for a one acre site as a reference point. Change the acreage in the tool below and the answer, and its reasoning, change with it.
Coverage
Permit coverage required
The project disturbs 1 acres, at or above the 1 acre threshold, so it needs permit coverage.
Determined against dataset version 2026-07-19.
Read these before you act on the answer
- Requirements below are what we have read and cited directly from Kansas Water Pollution Control General Permit and Authorization to Discharge, Stormwater Runoff from Construction Activities Under the National Pollutant Discharge Elimination System (General Permit No. S-MCST-2208-1, Federal Permit No. KSR100000), not the federal CGP. A category we have not yet transcribed from this permit is omitted here rather than assumed to match EPA's rule.
- The permit does not define a specific 'qualified' credential for the person performing routine site inspections (only the SWP2 Plan preparer must be a licensed PE/geologist/architect/landscape architect or CPESC), so inspection.qualifiedPerson is omitted. No increased inspection frequency for sensitive waters or reduced frequency for arid/semi-arid/drought conditions was found; KS instead has a distinct 'inactive site' reduced-inspection provision (modeled as state.ks.inspection.inactiveSite). KS does not use federal's acreage-tiered (<=5 acres / >5 acres) final stabilization completion structure -- it applies a single uniform 14-day stabilization-completion rule regardless of acreage -- so stabilization.complete.fiveAcresOrLess/moreThanFiveAcres were not used; a new state.ks.* id was created instead. No specific numeric-day deadline for filing the Notice of Termination (NOT) after project completion was found in the fetched text, so deadline.not.submission is omitted.
- Kansas requires a credentialed preparer. Treat the generated document as a complete draft for that person to review, adopt and sign. It is not by itself a compliant filed plan.
- Basinwise does not perform the physical site inspections the permit requires. Those must be carried out on site by a qualified person.
How this answer was reached, step by step
- 1
Coverage threshold
The project disturbs 1 acres, at or above the 1 acre threshold, so it needs permit coverage.
- 2
Permitting authority
Kansas. The state runs its own programme under KSR100000.
- 3
Preparer credential
Kansas requires a credentialed preparer. Treat the generated document as a complete draft for that person to review, adopt and sign. It is not by itself a compliant filed plan.
Verified2022 Kansas Construction Stormwater General Permit, General Permit No. S-MCST-2208-1 / Federal Permit No. KSR100000, Part 7.1Source
What to do next
- 1. Confirm the governing permit. Read Kansas Water Pollution Control General Permit and Authorization to Discharge, Stormwater Runoff from Construction Activities Under the National Pollutant Discharge Elimination System (General Permit No. S-MCST-2208-1, Federal Permit No. KSR100000) directly. It is linked above, and it is the document an inspector will hold you to. Kansas Department of Health and Environment (KDHE), Bureau of Water
- 2. Settle the preparer question before you draft. Getting this wrong costs a redraft at best. The detail is on the credential page for this state. Preparer credential in Kansas
- 3. Screen the site. Run the real acreage and receiving water facts through the tool below. You get the inspection frequency, the stabilisation deadlines and the filing path with the permit section behind each.
- 4. Read the requirements in full. SWPPP requirements in Kansas
Screen a Kansas site now
Runs in your browser. Nothing about the site is transmitted.
What people ask about the Kansas construction stormwater permit
Do I need a stormwater permit for a construction site in Kansas?
Permit coverage is triggered at one acre of land disturbance, and below one acre if the project is part of a larger common plan of development or sale that will ultimately disturb an acre or more. The project disturbs 1 acres, at or above the 1 acre threshold, so it needs permit coverage.
Who issues the construction stormwater permit in Kansas?
Kansas Department of Health and Environment (KDHE), Bureau of Water issues Kansas Water Pollution Control General Permit and Authorization to Discharge, Stormwater Runoff from Construction Activities Under the National Pollutant Discharge Elimination System (General Permit No. S-MCST-2208-1, Federal Permit No. KSR100000).
Does Kansas require a qualified preparer for the plan?
Kansas requires a credentialed preparer. Treat the generated document as a complete draft for that person to review, adopt and sign. It is not by itself a compliant filed plan.
Keep the record Kansas will ask you for
The screening is free. Holding the written plan and the retained inspection log is what the permit actually demands.